Town of Bridgewater Fee Schedule effective 7/1/2024
- Commercial/Industrial/Institutional Building Permit Fees
- Commercial Electrical Permit Fees
- Commercial Plumbing and Gas Permit Fees
- Residential Building Permit Fees
- Residential Electrical Permit Fees
- Residential Plumbing and Gas Permit Fees
Commercial/Industrial/Intuitional Building Permit Fee Schedule
Notes below correspond to Commercial/Industrial/Intuitional Building and Commercial/Industrial/Intuitional Miscellaneous Building Permits:
- Demolition value will be based on the current Town of Bridgewater’s assessment.
- All fees shall be rounded up to the nearest $1.00.
- If a return inspection is required due to faulty work or failure to keep an appointment, a $50.00 re-inspection fee shall be imposed.
- Estimated construction cost will be rounded up to the nearest $1,000.
- The Building Department reserves the right question the estimated Construction Cost.
- The above-listed permit fee shall be doubled where work requiring a permit has commenced prior to permitting; however, payment of such a fee shall not affect the penalty for violation prescribed in Chapter 1, Section 114.4 of the MA State Building Code. Starting work without a permit may be subject to non-criminal citation issued by the Bridgewater Building Department.
- Paper applications are accepted; however, an additional $50.00 administrative fee will be applied.
Commercial Electrical Fees
- The Electrical Inspector reserves the Right to establish fair market value of work in order to calculate permit fee. Calculation results in fraction of dollar, fee is founded to the next dollar.
- All work shall be done in accordance with the requirements of the Massachusetts Electrical Code and Regulations of National Grid. Service entrance locations must be obtained from National Grid.
- Paper applications are accepted; however, an additional $50.00 administrative fee will be applied.
| License/Permit/Fee | |
|---|---|
| All Work under this category unless specifically listed below | $ 150.00 plus 2% of value of work * |
| Institutional Permits for Maintenance and Alterations, Per chapter 141, Section 8 MGL Minimum (first person) | 300.00/year |
| Institutional Permits for Maintenance and Alterations, Per chapter 141, Section 8 MGL For each additional person performing electrical work | 225.00/year |
| Electric Signs | $200.00 |
| Burglar Alarm | $ 150.00 plus 2% of value of work |
| Fire Alarm | $ 150.00 plus 2% of value of work |
| Solar – (must have copy of contract) | $ 300.00 plus 2% of value of work |
| Carnivals, Circuses, Tents | $100.00 |
| Reinspection for Failed Inspection | $100 in Advance |
| Failure to Apply for a Permit | Triple Permit Fee |
| Inspection Outside of Office Hours | $100.00, 4-hour min. |
Commercial Plumbing and Gas Fees
- All Gas Permits requiring a test will be charged for the test as 1 fixture.
- Paper applications are accepted; however, an additional $50.00 administrative fee will be applied.
| License/Permit/Fee | |
|---|---|
| Plumbing | $ 125 for application plus $25.00 per fixture |
| Gas | $ 125 for application plus $25.00 per fixture |
| Water Heating (Only fixture on Permit) Plumbing | $120.00 |
| Water Heating (Only fixture on Permit) Gas | $120.00 |
| Water Heating Electric (Requires Wiring Permit) | 100.00 + 2% of the value of the job. |
| Sewer Connection (Submit on separate plumbing permit application and obtain registration number from Sewer Department ) | $100.00 |
| Re-Inspection | $75.00 |
| Failure to Apply for Permit | Triple Permit Fee |
| Emergency Inspection Outside of Office Hours (When called out by Fire Department or Utility Company) | 100.00, or fraction thereof, 4-hour min. |
Residential Building Permit Fees
Notes below correspond to Residential Building and Residential Miscellaneous Building Permits:
- Demolition value will be based on the current Town of Bridgewater’s assessment.
- All fees shall be rounded up to the nearest $1.00.
- If a return inspection is required due to faulty work or failure to keep an appointment, a $50.00 re-inspection fee shall be imposed.
- Estimated construction cost will be rounded up to the nearest $1,000.
- The Building Department reserves the right to question the estimated Construction Cost.
- The permit fee shall be doubled where work requiring a permit has commenced prior to permitting; however, payment of such a fee shall not affect the penalty for violation prescribed in Chapter 1, Section 114.4 of the MA State Building Code. Starting work without a permit may be subject to non-criminal citation issued by the Bridgewater Building Department.
- Paper applications are accepted; however, an additional $50.00 administrative fee will be applied.
| License/Permit/Fee | |
|---|---|
| Accessory structures 150 sq ft and up | $12/$1,000 – Minimum $100 |
| Shed 150 sq ft | $12/$1,000 – Minimum $100 |
| Above Ground Pool | $16/$1,000 – Minimum $200 |
| Inground Pool | $16/$1,000 – Minimum $300 |
| Tents/Trailer | $75 per tent/trailer – Minimum $75 |
| Decks | $12/$1,000 – Minimum $150 |
| Roofing | 1% of Value -- Minimum $100.00 |
| Siding | 1% of Value -- Minimum $100.00 |
| Stove Permit | $75 |
| Zoning Determination Certificate | $50 |
| Start Work Without a Permit | Triple Permit Fee |
| Duplicate Permit Card | $30 |
| Re-Inspection Fee | $100 |
| Temporary Occupancy Permit | $50 per unit |
| Occupancy Permit | $50 per unit |
| Multi-Family Certificate of Inspection per 780 CMR | $200 up to 4 units + $50 per unit after 4 |
| Fire Department Inspection Fee | $100 up to 4 units + $30 per unit after 4 |
| DBA Certificates requiring Inspections | $100 |
| Emergency Inspection Outside of Office Hours (When called out by Fire Department or Utility Company) | $ 75.00, or fraction thereof, 4-hour min. |
Residential Electrical Permit Fees
- The Electrical Inspector reserves the Right to establish fair market value of work in order to calculate permit fee. Calculation results in fraction of dollar, fee is founded to the next dollar.
- Paper applications are accepted; however, an additional $50.00 administrative fee will be applied.
- All work shall be done in accordance with the requirements of the Massachusetts Electrical Code and Regulations of National Grid. Service entrance locations must be obtained from National Grid.
- Permit number must accompany all inspection requests. Permits are valid for one year from the date of issue. Permit applicants are required to arrange for inspections upon completion of work. MGL 143 3L
| License/Permit/Fee | |
|---|---|
| Single Family Dwelling, including Service | $275.00 |
| Duplex Dwelling Two Family Dwelling Units | $400.00 |
| Additions or Rewiring Existing | $125.00 |
| Add Outlets to Existing Dwelling | $85.00 |
| Install Burglar Alarm or Low voltage Wiring | $100.00 |
| Oil Burners or Gas Heating System | $85.00 |
| Air Conditioning/Heat Pump System | $125.00 |
| Major Appliances (Installed at same time) | $85 each |
| Swimming Pool: Above Ground | $125.00 |
| Swimming Pool: In-ground | $175.00 |
| Wells | $125.00 |
| Residential Generator | $125.00 |
| Hot Tub | $100.00 |
| Pool Shed/Cabana | $125.00 |
| Storage Shed/Detached Garage | $125.00 |
| Solar Panels | $300.00 |
| EV Car Charger | $100.00 |
| Energy Storage System | $150.00 |
| New, Replace Existing or Upgrade Service | $125.00 |
| Temporary Service | $100.00 |
| Disconnect and Reconnect for Siding Service | $100.00 |
| Reinspection | $100.00 |
| Failure to Apply for a Permit | Triple Permit Fee |
| Emergency Inspection Outside of Office Hours (When called out by Fire Department or Utility Company | $ 100.00, 4-hour min. |
Residential Plumbing and Gas Fees
RESIDENTIAL - (Anything more than a three-family dwelling is considered to be commercial)
- All Gas Permits requiring a test will be charged for the test as 1 fixture.
- Paper applications are accepted; however, an additional $50.00 administrative fee will be applied.
| License/Permit/Fee | Current Amount | |
|---|---|---|
| Plumbing | $50.00 for application plus $15.00 per fixture | $65.00 for application plus $15.00 per fixture |
| Gas | $50.00 for application plus $15.00 per fixture | $65.00 for application plus $15.00 per fixture |
| Water Heating (Only fixture on Permit) Plumbing | $60.00 | $70.00 |
| Water Heating (Only fixture on Permit) Gas | $60.00 | $70.00 |
| Water Heating Electric (Requires Wiring Permit) | $75.00 | $75.00 |
| Sewer Connection (Submit on separate plumbing permit application and obtain registration number from Sewer Department ) | $60.00 | $60.00 |
| Re-Inspection | $60.00 | $75.00 |
| Failure to Apply for Permit | Double Permit Fee | Triple Permit Fee |
| Emergency Inspection Outside of Office Hours (When called out by Fire Department or Utility Company) | 75.00, or fraction thereof, 4-hour min. | 75.00, or fraction thereof, 4-hour min. |