Water System Improvement Updates

graphics shape

Plymouth Street Treatment Site Construction Updates

The Town will continue to provide weekly construction photo updates as work progresses at the Plymouth Street Treatment Site. Each weekly update includes a PDF photo packet showing recent site work and progress.

Weekly Update

August 6, 2026 Update

Construction progress at the Plymouth Street Treatment site remains steady across electrical, Drain line, and SCADA control systems. Electrical contractors are currently installing conduits connecting panels to data acquisition points, while Dig It Construction continues final grading of the lagoon area in preparation for liner installation and drain line pressure testing next week. Additionally, Our SCADA integrator is actively collaborating with filter manufacturers and their technical teams to ensure a seamless transition during the upcoming startup phase. 

Week 15

Latest Update

Construction continues to progress at the Plymouth Street Treatment site. Electrical conduit installation is underway, final lagoon grading is nearing completion ahead of liner installation and drain line testing, and SCADA integration work continues in preparation for system startup.

View Week 15 Photo PDF

Week 14

Contractors connected filter pads to process water lines and installed the finished-water booster pump. Sewer drain and lagoon work also advanced, while electrical crews continued preparations for the initial startup phase.

View Week 14 Photo PDF

Week 13

PFAS filters were delivered and placed on their pedestals, manifold piping began, electrical work continued on the booster pumps, and construction started on the lagoon and drain system.

View Week 13 Photo PDF

Previous Weekly Updates

Open the archive below to view construction summaries and photo PDFs from Weeks 1–12.

View Previous Weekly Updates Weeks 1–12 construction summaries and photo PDFs
Week 12 — Filter media loading, automation work and PFAS filter preparation
View PDF
Week 11 — Electrical work, filter media loading and system piping
View PDF
Week 10 — PFAS equipment pedestals and SCADA infrastructure
View PDF
Week 9 — Chemical feed systems and startup preparation
View PDF
Week 8 — Pressure testing, conduit installation and PFAS preparation
View PDF
Week 7 — Filter piping, sampling infrastructure and pressure testing
View PDF
Week 6 — Continued construction of the Wells 10A and 10B treatment systems
View PDF
Week 5 — Equipment delivery, placement and piping progress
View PDF
Week 4 — Utility work, concrete pads and treatment system preparation
View PDF
Week 3 — Filter pedestal and PFAS pad preparation
View PDF
Week 2 — Storage areas, test pits, well house work and site preparation
View PDF
Week 1 — Early site work, concrete pads, valves and utility identification
View PDF