Emergency Conserve Water: Mandatory Outdoor Water Use Restrictions
More Information
close icon

Water System Improvement Updates

graphics shape

Plymouth Street Treatment Site Construction Updates

The Town will continue to provide weekly construction photo updates as work progresses at the Plymouth Street Treatment site. Each weekly update includes a PDF photo packet showing recent site work and progress.

Weekly Update

June 17, 2026 Update

Construction activity continues at the Plymouth Street treatment site. Work continues to progress on the new water treatment systems for Wells 10A and 10B. This week, our contractor dug test pits for the lagoon, began pressure testing the backwash supply lines, ran electrical conduit, and prepped the forms for the concrete pedestals for the PFAS Filters.  

Click below to view weekly construction photo packets.

📷 Construction Photo Archive 

Select a week below to view available construction photo packets. Future weeks will be added as construction progresses.

Week 1

Early site work, concrete pad preparation, valve installation, test pits, and water line identification.

View Photo PDF

Week 2

Chemical storage areas, core cuts, existing well house work, PFAS system preparation, and site preparation.

View Photo PDF

Week 3

Pedestal preparation for the iron and manganese filters, PFAS pad preparation, and waterline infrastructure staging.

View Photo PDF

Week 4

Continued treatment site construction, utility work, concrete pad progress, and preparation for upcoming treatment system installation.

View Photo PDF

Week 5

Continued site work, delivery and placement of treatment equipment, piping progress, and ongoing preparation for the Plymouth Street Treatment system.

View Photo PDF

Week 6

Construction activity continues at the Plymouth Street treatment site as work progresses on the new water treatment systems for Wells 10A & 10B.

View Photo PDF

Week 7

Work continues at the Plymouth Street treatment site on the new water treatment systems for Wells 10A and 10B. Crews are completing filter piping, installing sampling infrastructure, and preparing for pressure testing this week.

View Photo PDF

Week 8

Crews continued work on the new treatment systems for Wells 10A and 10B, including lagoon test pits, backwash line pressure testing, electrical conduit installation, and preparation of concrete pedestals for the PFAS filters.

View Photo PDF

Week 9

Coming soon.

Week 10

Coming soon.

Additional Updates

Additional weekly construction updates and photo packets will be posted as construction progresses.